Under construction
ROYAL VILLASMahaRERA P51700077636
CTS NO 3535, PLOT NO 7, FINAL PLOT NO 7 MAUJE BHIWANDI, MOUJE BHIWANDI, 421302
Mar 2027
Possession
83.8%
Built
0
Complaints
7
Units
Caution
- Possession delayed ~1 yr. Originally promised Dec 2025, now proposed Mar 2027 per the RERA filing.
Official RERA facts
- Registration
- P51700077636
- Status
- New
- Stage
- Certificate Signed
- Possession
- March 2027originally December 2025
- Construction
- 83.8% complete
- Units sold
- 1 of 7
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 22 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationdone
Open Parkingdone
Building & registration
- RERA registered
- Oct 2024
- Floors
- 2
- Unit mix
- 7 res ยท 0 comm
- Architect
- PLAN HIGH MANAGEMENT CONSULTANTS
Buyer community
Connect with other buyers and owners of ROYAL VILLAS โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching ROYAL VILLAS. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.