RUKMINI SMRUTI CO OP SOCIETY LTDMahaRERA P51700078193

by GLOBAL ENTERPRISES

PLOT NO 10 S NO 326/A (PT)(OLD)S NO 229/B/10(NEW), NAVAGAON, 421202

Jun 2027
Possession
0%
Built
0
Complaints
16
Units
High risk
  • Behind schedule. Possession is due Jun 2027 but construction is only at 0%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2027 per the RERA filing.

Official RERA facts

Registration
P51700078193
Status
New
Stage
Certificate Signed
Possession
June 2027
Construction
0% complete
Units sold
0 of 16

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Nov 2024
Floors
8
Unit mix
16 res ยท 0 comm
Architect
R K ASSOCIATES B S RANADE

Buyer community

Connect with other buyers and owners of RUKMINI SMRUTI CO OP SOCIETY LTD โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching RUKMINI SMRUTI CO OP SOCIETY LTD. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.