OM APARTMENT
by SUNNY REALTY
58/2/N PLOT NO 9, VANGANI, 421503
- Behind schedule. Possession is due Jun 2027 but construction is only at 46.8%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2027 per the RERA filing.
Official RERA facts
- Registration
- P51700080473
- Status
- New
- Stage
- Certificate Signed
- Possession
- June 2027
- Construction
- 46.8% complete
- Units sold
- 8 of 33
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 24 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Jun 2025
- Floors
- 8
- Unit mix
- 29 res ยท 4 comm
- Plot / CTS / survey no.
- 58/2/N PLOT NO 9
- Planning authority
- collector thane
- Approved layout land
- 541 sq.m
- Land for this registration
- 541 sq.m
- Recreational open space
- 0 sq.m
- Permissible built-up area
- 1,222.09 sq.m
- Registered office
- SAI SAMARTH APARTMENT
- North
- ADJ PLOT NO 8
- South
- ADJ PLOT NO 10
- East
- ADJ H NO 2A
- West
- 9 M WIDE ROAD
Project bank account
The RERA-designated account this project's payments should go to โ verify before wiring any money.
- ICICI BANK LIMITED โ 65276IFSC ICIC0003402ICICI Bank Ltd., Ground Floor, Shop No. 10 to 12, Maitri Vatika Bldg, Parsik Nagar, Old Mumbai Pune Highway, Kalwa W, Thane.400605, Maharashtra.400605
Commencement Certificate documents
- CC COPY KIRAN CHAVAN.pdf
Buyer community
Connect with other buyers and owners of OM APARTMENT โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching OM APARTMENT. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.