OZONE GALAXY Phase III

MahaRERA P51700080793High risk

by HALLMARK INFRA REALTY LLP

64/10, 65/1, 65/3A, 65/3B, 66/5, 66/8, 68/7, 68/14, OZONE GALAXY NEAR YOGESHWAR BUNGLOW, 421302

Official record
Dec 2026
Possession
27.3%
Built
0
Complaints
76
Units
High risk
  • Possession delayed ~1 yr. Originally promised Dec 2025, now proposed Dec 2026 per the RERA filing.
  • Behind schedule. Possession is due Dec 2026 but construction is only at 27.3%.

Official RERA facts

Registration
P51700080793
Status
New
Stage
Certificate Signed
Possession
December 2026originally December 2025
Construction
27.3% complete
Units sold
19 of 76

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 24 Jul 2026).

Possession extension history

  • EA29122519075Revised to December 2026

    The delay in completion of the project is attributable to circumstances beyond the control of the promoter, primarily due to prolonged processing time by the concerned statutory authorities for grant of requisite approvals and registrations. The construction schedule was consequently impacted as further progress was dependent on receipt of such approvals. The promoter has at all times complied with the applicable provisions of the RERA Act and allied regulations and has taken all reasonable steps to expedite the approval process.

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths80%
Water Supply80%
Sewerage (Chamber, Lines, Septic Tank , STP)80%
Landscaping & Tree Planting80%
Street Lighting80%
Community Buildings80%
Water conservation /Rain water harvesting80%
Fire protection and fire safety requirements80%
Electrical meter room, sub-station, receiving station80%
Aggregate area of recreational Open Space80%
Open Parking80%

Building & registration

RERA registered
Jul 2025
Floors
9
Unit mix
76 res ยท 0 comm
Architect
Atul Anil Gharat
Plot / CTS / survey no.
64/10, 65/1, 65/3A, 65/3B, 66/5, 66/8, 68/7, 68/14
Planning authority
Mumbai Metropolitan Region Development Authority
Approved layout land
4,273.42 sq.m
Land for this registration
4,273.42 sq.m
Recreational open space
253.86 sq.m
Permissible built-up area
4,273.42 sq.m
Registered office
S P SOCIETY
Plot boundaries
North
119M
South
141M
East
78M
West
73M
Parking
24 four-wheeler

Project bank account

The RERA-designated account this project's payments should go to โ€” verify before wiring any money.

  • G P PARSIK BANK โ€” 94164
    IFSC PJSB0000003
    KALWA BRANCH, CREEK VIEW APARTMENT, 1ST FLOOR, BOMBAY PUNE ROAD,KALWA, THANE - 400 605.

Commencement Certificate documents

  • Work Start Notice (1).pdf
  • SKM_C250i-m25032614330 (1).pdf
  • Commencement Certificate Building C.pdf

Buyer community

Connect with other buyers and owners of OZONE GALAXY Phase III โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching OZONE GALAXY Phase III. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.