127 UPPER EAST
by PARANJAPE SCHEMES (CONSTRUCTION) LTD
CTS No. 2059 and 2073 Final Plot No. 127 of TPS - V, Andheri, 400055
- Possession delayed ~4 yrs. Originally promised Dec 2019, now proposed Jun 2024 per the RERA filing.
- Possession date passed. The proposed possession date (Jun 2024) has passed with construction at 56.4%.
- Promised amenities not started. Swimming Pool, Gymnasium, Landscaped Garden are at 0% build with possession due Jun 2024 per the RERA filing.
Bandra's quieter northern neighbour โ low-rise lanes going boutique.
- Growth drivers:
- Society redevelopment, airport and BKC equidistance.
- Who buys here:
- Professionals wanting Bandra adjacency with less noise.
PropPin area guide โ editorial, not a RERA disclosure.
Official RERA facts
- Registration
- P51800000454
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- June 2024originally December 2019
- Construction
- 56.4% complete
- Units sold
- 0 of 0
RERA complaint record1 record
- ComplaintCC00600000039723026 Aug 2023Avinash Narayan Mahale vs M/s Paranjape Scheme (Construction) LimitedOrder of Avinash Mahale.pdf on MahaRERA
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Jul 2017
- Floors
- 11
Buyer community
Connect with other buyers and owners of 127 UPPER EAST โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching 127 UPPER EAST. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.