Under construction

Kalpataru Radiance C

by Keyana Estate LLP

CTS no.260/5A -part of village Pahadi Goregaon west, Borivali, 400104

High risk
  • Recovery warrant issued. MahaRERA has issued 1 recovery warrant against this project โ€” the strongest enforcement action on record.
  • Possession delayed ~2 yrs. Originally promised Jun 2022, now proposed Dec 2023 per the RERA filing.
  • 37 RERA complaints. 37 complaint records are disclosed against this project on MahaRERA.
  • Possession date passed. The proposed possession date (Dec 2023) has passed with construction at 97%.
GoregaonUpper-mid

Film City flank with large integrated townships on both flanks.

Growth drivers:
Oberoi/NESCO belt, Metro 7, Western Express Highway offices.
Who buys here:
Upgraders wanting township amenities without Powai prices.

PropPin area guide โ€” editorial, not a RERA disclosure.

Official RERA facts

Registration
P51800000482
Status
Ongoing
Stage
Certificate Signed
Possession
December 2023originally June 2022
Construction
97% complete
Units sold
0 of 0

RERA complaint record37 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths92%
Water Supply75%
Sewerage (Chamber, Lines, Septic Tank , STP)75%
Storm Water Drainsdone
Landscaping & Tree Planting78%
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposal60%
Water conservation /Rain water harvesting80%
Energy managemcnt30%
Fire protection and fire safety requirements70%
Electrical meter room, sub-station, receiving station73%
Aggregate area of recreational Open Spacenot started
Open Parkingnot started
Club House,Fitness Centre Swimming pool & other Recreation areas27%
3 Nos. of Common Podiums/E-deck81%
2 Nos. of Common Basements80%

Building & registration

RERA registered
Jul 2017
Floors
38
Architect
Space Moulders

Buyer community

Connect with other buyers and owners of Kalpataru Radiance C โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Kalpataru Radiance C. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.