Jul 2024
Possession
90.9%
Built
18
Complaints
0
Units
High risk
- Possession delayed ~5 yrs. Originally promised Dec 2019, now proposed Jul 2024 per the RERA filing.
- 18 RERA complaints. 18 complaint records are disclosed against this project on MahaRERA.
- Possession date passed. The proposed possession date (Jul 2024) has passed with construction at 90.9%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Jul 2024 per the RERA filing.
Kurla / ChemburMid-income
Central crossroads reborn via freeway and Metro links.
- Growth drivers:
- Eastern Freeway, Monorail/Metro, BKC proximity at half the price.
- Who buys here:
- BKC-bound professionals and long-time Chembur families.
PropPin area guide โ editorial, not a RERA disclosure.
Official RERA facts
- Registration
- P51800001050
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- July 2024originally December 2019
- Construction
- 90.9% complete
- Units sold
- 0 of 0
RERA complaint record18 records
- ComplaintCC125000091 Jan 2025Rajesh Jhunjhunwala vs Ganesh Praful Tondwalkar2 3.pdf on MahaRERA
- ComplaintCC125000081 Jan 2025Rajesh Jhunjhunwala vs Anil Kishinchand Rajani2 3.pdf on MahaRERA
- ComplaintCC00600000029265014 Sept 2022Smriti Parekh vs spenta enclave pvt ltdCC006000000292650 disposal roznama.pdf on MahaRERA
- ComplaintCC00600000022113016 May 2022Ganesh Praful Tondwalkar vs SPENTA ENCLAVE PVT. LTDOrder CC6193129 CC6221130 Anil Rajani Vs Spenta Enclave signed.pdf on MahaRERA
- ComplaintCC0060000001981635 Dec 2021MANISH AGARWAL vs SPENTA ENCLAVE PVT LTD198163.pdf on MahaRERA
- ComplaintCC0060000001975497 Jul 2021Mr Shrinivas Manche & Mrs Vanita Manche vs Spenta Enclave Private LimitedOrder-P51800001050 (7) signed.pdf on MahaRERA
- ComplaintCC00600000019598914 May 2021Urvanki I Shah vs Spenta Enclave Pvt LtdOrder-P51800001050 (7) signed.pdf on MahaRERA
- ComplaintCC00600000019620328 Feb 2021Rajan Singh Chugh vs Alta Vista Builder Builder Spenta CorporationCC 006 196203 Scan Order Sr 16 Dated 16 02 2022.pdf on MahaRERA
- ComplaintCC00600000019608017 Feb 2021Debanik Basu vs Spenta Enclave Private LimitedOrder-P51800001050 (7) signed.pdf on MahaRERA
- ComplaintCC00600000019532521 Dec 2020Monish Satwe vs Spenta Enclave Pvt. Ltd.Order-P51800001050 (7) signed.pdf on MahaRERA
- ComplaintCC00600000019532821 Dec 2020Monish Satwe vs Spenta Enclave Pvt. Ltd.Order-P51800001050 (7) signed.pdf on MahaRERA
- ComplaintCC00600000019473431 Oct 2020Geeta PramodKumar Gupta vs SPENTA ENCLAVE PRIVATE LIMITEDCC 006 19434 Scan Order Sr 15 Dated 16 02 2022.pdf on MahaRERA
- ComplaintCC00600000019350428 Jul 2020Mr. Dhirendra Kumar Sinha and Mrs. Devyani Singh vs Spenta Enclave Private LimitedDisposal Order Sr No 74 signed.pdf on MahaRERA
- ComplaintCC00600000019359827 Jul 2020Amisha Ghia vs Spenta Enclave Pvt LtdScan order CC006-193598 dated 06-06-2022.pdf on MahaRERA
- ComplaintCC00600000019312925 Jul 2020Anil Kishinchand Rajani vs Spenta Enclave Private LimitedOrder CC6193129 CC6221130 Anil Rajani Vs Spenta Enclave signed.pdf on MahaRERA
- ComplaintCC00600000019327910 Jun 2020Mrs Sneha Vijay Nair and Mr Vijaykumar Madhavan vs Spenta Enclave Private LimitedOrder-P51800001050 (7) signed.pdf on MahaRERA
- ComplaintCC0060000001821118 Jan 2020Umesh Prabhakar Dhopate and Pranita Umesh Dhopate vs Spenta Enclave Pvt LtdOrder-P51800001050 (7) signed.pdf on MahaRERA
- ComplaintCC0060000000122421 Dec 2017Subhash Bawa vs Spenta Enclave Private Limited12242 Subhash Bawa Vs Spenta Enclave Pvt Ltd.pdf on MahaRERA
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposaldone
Water conservation /Rain water harvestingdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Spacenot started
Building & registration
- RERA registered
- Jul 2017
- Floors
- 29
Buyer community
Connect with other buyers and owners of Altavista - Phase 1 โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching Altavista - Phase 1. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.