Boulevard Tower 5

by Acme Realties Private Limited

CTS Nos 160/A/1 and 162 of Village Majas part-I CTS Nos 163 and 165 of Village Majas part-II and CT, Andheri, 400060

High risk
  • Possession delayed ~4 yrs. Originally promised Dec 2022, now proposed Jun 2027 per the RERA filing.

Official RERA facts

Registration
P51800001690
Status
New
Stage
Certificate Signed
Possession
June 2027originally December 2022
Construction
79.1% complete
Units sold
123 of 152

RERA complaint record

Complaint data not yet synced for this project.