PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

GLORIS

by Sahakar Developers

1113/A TO 1113/D, Borivali, 400068

High risk
  • Possession date passed. The proposed possession date (Dec 2019) has passed with construction at 80.5%.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Dec 2019 per the RERA filing.
Dahisar / Mira RoadValue

The city's northern value frontier, densifying fast.

Growth drivers:
Metro 9 extension, spillover from Borivali pricing.
Who buys here:
First-time buyers stretching for a 1โ€“2 BHK.

PropPin area guide โ€” editorial, not a RERA disclosure.

Official RERA facts

Registration
P51800001984
Status
Ongoing
Stage
Certificate Signed
Possession
December 2019originally December 2018
Construction
80.5% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 20 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply79%
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drains75%
Landscaping & Tree Plantingnot started
Community Buildingsnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving station90%

Building & registration

RERA registered
Jul 2017
Floors
21

Buyer community

Connect with other buyers and owners of GLORIS โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching GLORIS. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.