All RERA projects
🏗️
Under construction

SHREYA

by BHARAT NAVINCHANDRA GALA

473/473/1 T0 5, Borivali, 400064

High risk
  • Possession delayed ~7 yrs. Originally promised Dec 2018, now proposed Jun 2026 per the RERA filing.
  • Possession date passed. The proposed possession date (Jun 2026) has passed with construction at 36.2%.

Official RERA facts

Registration
P51800002243
Status
Ongoing
Stage
Certificate Signed
Possession
June 2026originally December 2018
Construction
36.2% complete
Units sold
0 of 0

RERA complaint record

Complaint data not yet synced for this project.