All RERA projects
🏗️
Under construction

Skyline viha Wing B

by Ankit Overseas

460 A pt 460 3 to 7, Kurla, 400086

High risk
  • Possession delayed ~5 yrs. Originally promised Dec 2018, now proposed Jun 2024 per the RERA filing.
  • Possession date passed. The proposed possession date (Jun 2024) has passed with construction at 82.6%.

Official RERA facts

Registration
P51800002495
Status
Ongoing
Stage
Certificate Signed
Possession
June 2024originally December 2018
Construction
82.6% complete
Units sold
48 of 76

RERA complaint record

Complaint data not yet synced for this project.

Discussion

No discussions yet. Booked here, visited the site, or got a quote? Share it — buyers in the same project rarely get to compare notes.

Start a discussion

Data sourced from the official MahaRERA portal. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.