AMAZON PARK BUILDING NO 2 - WING C

by R.J. CONSTRUCTIONS

CTS NO. 532 PT, 1541, 1533 AND 1532, BORIVALI WEST, 400103

Mar 2025
Possession
53.6%
Built
14
Complaints
0
Units
High risk
  • Possession delayed ~4 yrs. Originally promised Jun 2021, now proposed Mar 2025 per the RERA filing.
  • 14 RERA complaints. 14 complaint records are disclosed against this project on MahaRERA.
  • Possession date passed. The proposed possession date (Mar 2025) has passed with construction at 53.6%.

Official RERA facts

Registration
P51800002956
Status
New
Stage
Certificate Signed
Possession
March 2025originally June 2021
Construction
53.6% complete
Units sold
0 of 0

RERA complaint record14 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Street Lightingdone
Treatment And Disposal Of Sewage And Sullage Waterdone
Solid Waste Management And Disposaldone
Water conservation /Rain water harvestingdone
Energy managemcntdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
LIGHTNING ARRESTERdone

Building & registration

RERA registered
Aug 2017
Floors
18

Buyer community

Connect with other buyers and owners of AMAZON PARK BUILDING NO 2 - WING C โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching AMAZON PARK BUILDING NO 2 - WING C. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.