PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

Hirkani Co-operative Housing Society

by Vraj Kamman Real Estate Developers Private Limited

120,120/1 to 9, Borivali, 400063

High risk
  • Possession delayed ~4 yrs. Originally promised Dec 2023, now proposed Dec 2027 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2027 per the RERA filing.

Official RERA facts

Registration
P51800003206
Status
Ongoing
Stage
Certificate Signed
Possession
December 2027originally December 2023
Construction
90.9% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 20 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started
Intercom Facilitynot started
Wifi Facilitynot started
CCTV Facilitynot started
AC Entrance Lobbynot started

Building & registration

RERA registered
Aug 2017
Floors
9

Buyer community

Connect with other buyers and owners of Hirkani Co-operative Housing Society โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Hirkani Co-operative Housing Society. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.