Caution
  • Behind schedule. Possession is due Dec 2026 but construction is only at 43.5%.

Official RERA facts

Registration
P51800004236
Status
Ongoing
Stage
Certificate Signed
Possession
December 2026
Construction
43.5% complete
Units sold
0 of 0