Under construction

Redevelopment of Jai Vijay CHSL - Phase I

by KOLTE-PATIL DEVELOPERS LIMITED

126/A, 126/B, 126/C, 126/D, 129, 129/1 and 129/2, Mumbai, 400099

High risk
  • Possession delayed ~3 yrs. Originally promised Sept 2019, now proposed Sept 2022 per the RERA filing.
  • Possession date passed. The proposed possession date (Sept 2022) has passed with construction at 63.6%.

Official RERA facts

Registration
P51800004446
Status
Ongoing
Stage
Certificate Signed
Possession
September 2022originally September 2019
Construction
63.6% complete
Units sold
0 of 0

RERA complaint record2 records

  • ComplaintCC0060000001936006 Sept 2020
    Mr. Ranjit Narayan Bhise vs Kolte Patil Developers Ltd.
  • ComplaintCC00600000019329015 Jun 2020
    Mr Manohar Shetty and Mrs Lalita M Shetty vs Kolte-Patil Developers Limited
    CC006000000193290.pdf on MahaRERA

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Street Lightingdone
Community Buildings95%
Treatment And Disposal Of Sewage And Sullage Waterdone
Solid Waste Management And Disposaldone
Water conservation /Rain water harvestingdone
Energy managemcntdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Space90%
Open Parkingnot started

Building & registration

RERA registered
Aug 2017
Floors
12

Buyer community

Connect with other buyers and owners of Redevelopment of Jai Vijay CHSL - Phase I โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Redevelopment of Jai Vijay CHSL - Phase I. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.