Integrated Arya

by Integrated Spaces Limited

183C/1 AND 183C/2, Kurla, 400086

High risk
  • Possession delayed ~10 yrs. Originally promised Mar 2019, now proposed Dec 2028 per the RERA filing.

Official RERA facts

Registration
P51800004521
Status
Ongoing
Stage
Certificate Signed
Possession
December 2028originally March 2019
Construction
83.5% complete
Units sold
82 of 167

RERA complaint record

Complaint data not yet synced for this project.