Under construction

Borivli Vasundhara CHS Ltd.

by Shree Sai Shraddha Developers

290/4-B, Borivali East, 400066

Dec 2025
Possession
72.7%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~6 yrs. Originally promised Jan 2020, now proposed Dec 2025 per the RERA filing.
  • Possession date passed. The proposed possession date (Dec 2025) has passed with construction at 72.7%.
GoregaonUpper-mid

Film City flank with large integrated townships on both flanks.

Growth drivers:
Oberoi/NESCO belt, Metro 7, Western Express Highway offices.
Who buys here:
Upgraders wanting township amenities without Powai prices.

PropPin area guide โ€” editorial, not a RERA disclosure.

Official RERA facts

Registration
P51800006294
Status
Ongoing
Stage
Certificate Signed
Possession
December 2025originally January 2020
Construction
72.7% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Landscaping & Tree Plantingdone
Street Lightingdone
Water conservation /Rain water harvestingdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Open Parkingnot started

Building & registration

RERA registered
Aug 2017
Floors
9

Buyer community

Connect with other buyers and owners of Borivli Vasundhara CHS Ltd. โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Borivli Vasundhara CHS Ltd.. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.