Dec 2028
Possession
65.9%
Built
2
Complaints
1
Units
High risk
- Possession delayed ~10 yrs. Originally promised Mar 2019, now proposed Dec 2028 per the RERA filing.
Kurla / ChemburMid-income
Central crossroads reborn via freeway and Metro links.
- Growth drivers:
- Eastern Freeway, Monorail/Metro, BKC proximity at half the price.
- Who buys here:
- BKC-bound professionals and long-time Chembur families.
PropPin area guide โ editorial, not a RERA disclosure.
Official RERA facts
- Registration
- P51800006968
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2028originally March 2019
- Construction
- 65.9% complete
- Units sold
- 1 of 1
RERA complaint record2 records
- ComplaintCC00600000029280026 Sept 2022RAMNARAYAN KUBER GUPTA vs Amber Capro Pvt. Ltd.RFO.pdf on MahaRERA
- Misc. applicationCC00600000029280026 Sept 2022RAMNARAYAN KUBER GUPTA vs Amber Capro Pvt. Ltd.
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Building & registration
- RERA registered
- Aug 2017
- Floors
- 17
- Unit mix
- 1 res ยท 0 comm
- Architect
- ritesh thakur
Buyer community
Connect with other buyers and owners of AMBER EMPIRE โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching AMBER EMPIRE. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.