Under construction

Avirahi Heights

by ABHIGNA ENTERPRISES

337/A 350/A, Borivali, 400092

High risk
  • Possession delayed ~3 yrs. Originally promised Dec 2019, now proposed Jun 2023 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2023 per the RERA filing.

Official RERA facts

Registration
P51800007245
Status
Ongoing
Stage
Certificate Signed
Possession
June 2023originally December 2019
Construction
100% complete
Units sold
94 of 97

RERA complaint record2 records

  • ComplaintCC00600000019885829 Oct 2021
    Mr. Dilip J. Kale vs Abhingna Enterprises & Anr.
    CC006_198858.pdf on MahaRERA
  • Misc. applicationCC00600000019885829 Oct 2021
    Mr. Dilip J. Kale vs Abhingna Enterprises & Anr.

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply50%
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingnot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirements50%
Electrical meter room, sub-station, receiving station50%

Building & registration

RERA registered
Aug 2017
Floors
24
Unit mix
97 res ยท 0 comm

Buyer community

Connect with other buyers and owners of Avirahi Heights โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Avirahi Heights. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.