All RERA projects
🏗️
Under construction

SANSKRUTI BUILDING NO 2 C WING

by NIRMAN REALTORS AND DEVELOPERS LTD

273 275 AND 276 S NO 20 H NO 714, Andheri, 400097

High risk
  • Possession delayed ~1 yr. Originally promised Dec 2025, now proposed Dec 2026 per the RERA filing.
  • Behind schedule. Possession is due Dec 2026 but construction is only at 43.8%.

Official RERA facts

Registration
P51800007436
Status
Ongoing
Stage
Certificate Signed
Possession
December 2026originally December 2025
Construction
43.8% complete
Units sold
0 of 1

RERA complaint record

Complaint data not yet synced for this project.

Discussion

No discussions yet. Booked here, visited the site, or got a quote? Share it — buyers in the same project rarely get to compare notes.

Start a discussion

Data sourced from the official MahaRERA portal. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.