PropPin
All RERA projects
🏗️
Under construction

SHIV KRUPA

by SHIV KRUPA DEVELOPERS

CTS 1173 A, Kurla, 400080

High risk
  • Possession date passed. The proposed possession date (Mar 2019) has passed with construction at 81.8%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2019 per the RERA filing.
MulundUpper-mid

Leafy eastern-suburb favourite with big redevelopment supply.

Growth drivers:
Eastern Express Highway, proposed Goregaon–Mulund link, mall belt.
Who buys here:
Eastern-suburb families upgrading within the area.

PropPin area guide — editorial, not a RERA disclosure.

Official RERA facts

Registration
P51800008179
Status
Ongoing
Stage
Certificate Signed
Possession
March 2019originally March 2018
Construction
81.8% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 20 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply90%
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirements90%
Electrical meter room, sub-station, receiving station90%
Open Parkingnot started

Building & registration

RERA registered
Aug 2017
Floors
12

Buyer community

Connect with other buyers and owners of SHIV KRUPA — compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet — start one and connect with the next buyer researching SHIV KRUPA. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.