High risk
  • Possession delayed ~3 yrs. Originally promised Dec 2023, now proposed Dec 2026 per the RERA filing.

Official RERA facts

Registration
P51800008480
Status
Ongoing
Stage
Certificate Signed
Possession
December 2026originally December 2023
Construction
87.5% complete
Units sold
142 of 166