Under construction

Pearl 2

by Pearl Building No -2 Co -Operative Housing Society Limited

G/346-19, Plot No 83- C/B-2, Andheri, 400054

Mar 2027
Possession
โ€”
Built
2
Complaints
15
Units
High risk
  • Possession delayed ~8 yrs. Originally promised Jul 2019, now proposed Mar 2027 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2027 per the RERA filing.
Santacruz / KharUltra-luxury

Bandra's quieter northern neighbour โ€” low-rise lanes going boutique.

Growth drivers:
Society redevelopment, airport and BKC equidistance.
Who buys here:
Professionals wanting Bandra adjacency with less noise.

PropPin area guide โ€” editorial, not a RERA disclosure.

Official RERA facts

Registration
P51800009076
Status
Ongoing
Stage
Certificate Signed
Possession
March 2027originally July 2019
Construction
โ€”
Units sold
14 of 15

RERA complaint record2 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supply10%
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started

Building & registration

RERA registered
Aug 2017
Floors
9
Unit mix
15 res ยท 0 comm

Buyer community

Connect with other buyers and owners of Pearl 2 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Pearl 2. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.