HERITAGE AHURA RESIDENCY

by KERSI JAMSHED RANDERIA

1774,1775,1776A,1777, Kurla, 400086

High risk
  • Possession delayed ~6 yrs. Originally promised Dec 2022, now proposed Dec 2028 per the RERA filing.

Official RERA facts

Registration
P51800009207
Status
Ongoing
Stage
Certificate Signed
Possession
December 2028originally December 2022
Construction
59.5% complete
Units sold
16 of 251

RERA complaint record

Complaint data not yet synced for this project.