Under construction

Royal Fantasy Phase I

by Royal Fantasy Constructions Private Limited

CTS No. 424, 424/1 to 33, Andheri, 400093

High risk
  • Possession delayed ~3 yrs. Originally promised Dec 2018, now proposed Jun 2022 per the RERA filing.
  • Possession date passed. The proposed possession date (Jun 2022) has passed with construction at 84.2%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2022 per the RERA filing.
Andheri East / MarolMid-income

Office corridors (SEEPZ, MIDC) with value housing pockets between them.

Growth drivers:
Airport proximity, Metro 1/7, IT-park employment.
Who buys here:
Working couples prioritising commute over frills.

PropPin area guide โ€” editorial, not a RERA disclosure.

Official RERA facts

Registration
P51800009606
Status
Ongoing
Stage
Certificate Signed
Possession
June 2022originally December 2018
Construction
84.2% complete
Units sold
0 of 0

RERA complaint record5 records

  • ComplaintCC00600000040853919 Dec 2023
    BHAGCHAND C BHANDARI vs ROYALFANTASYCONSTRUCTION PVT LTD
    Order_408539.pdf on MahaRERA
  • Misc. applicationCC00600000040853919 Dec 2023
    BHAGCHAND C BHANDARI vs ROYALFANTASYCONSTRUCTION PVT LTD
  • ComplaintCC00600000019847729 Sept 2021
    Farooq Ahmed Ansari vs Royal FantansyConstructions Pvt.Ltd
    198477 order.pdf on MahaRERA
  • Misc. applicationCC00600000019847729 Sept 2021
    Farooq Ahmed Ansari vs Royal FantansyConstructions Pvt.Ltd
  • ComplaintCC00600000010044216 Aug 2019
    Farooq Ahmed Ansari vs Royal Fantasy Construction Private Limited, Mr. Sajay Saraf (Director)
    Order of Farooq.pdf on MahaRERA

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)70%
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Water65%
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirements50%
Electrical meter room, sub-station, receiving station60%

Building & registration

RERA registered
Aug 2017
Floors
16

Buyer community

Connect with other buyers and owners of Royal Fantasy Phase I โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Royal Fantasy Phase I. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.