SUPRABHAT CLASSIC
114 A PART CSN 58 6 TO 9, Sahkar Nagar, 400071
Dec 2026
Possession
70.7%
Built
14
Complaints
0
Units
High risk
- Possession delayed ~8 yrs. Originally promised Dec 2018, now proposed Dec 2026 per the RERA filing.
- 14 RERA complaints. 14 complaint records are disclosed against this project on MahaRERA.
Official RERA facts
- Registration
- P51800009781
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2026originally December 2018
- Construction
- 70.7% complete
- Units sold
- 0 of 0
RERA complaint record14 records
Complaint data not yet synced for this project.
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Water Supply63%
Sewerage (Chamber, Lines, Septic Tank , STP)63%
Storm Water Drains63%
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirements63%
Electrical meter room, sub-station, receiving station63%
Building & registration
- RERA registered
- Aug 2017
- Floors
- 11
Buyer community
Connect with other buyers and owners of SUPRABHAT CLASSIC โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching SUPRABHAT CLASSIC. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.