SUPRABHAT CLASSIC

by DENNIS JAMES FERNANDES

114 A PART CSN 58 6 TO 9, Sahkar Nagar, 400071

Dec 2026
Possession
70.7%
Built
14
Complaints
0
Units
High risk
  • Possession delayed ~8 yrs. Originally promised Dec 2018, now proposed Dec 2026 per the RERA filing.
  • 14 RERA complaints. 14 complaint records are disclosed against this project on MahaRERA.

Official RERA facts

Registration
P51800009781
Status
Ongoing
Stage
Certificate Signed
Possession
December 2026originally December 2018
Construction
70.7% complete
Units sold
0 of 0

RERA complaint record14 records

Complaint data not yet synced for this project.

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply63%
Sewerage (Chamber, Lines, Septic Tank , STP)63%
Storm Water Drains63%
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirements63%
Electrical meter room, sub-station, receiving station63%

Building & registration

RERA registered
Aug 2017
Floors
11

Buyer community

Connect with other buyers and owners of SUPRABHAT CLASSIC โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SUPRABHAT CLASSIC. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.