SAFAL SAI AND SAFAL SAINATH
by MANGALNATH DEVELOPERS PVT LTD
CTS NO. 453,453 1 TO 74, 525, 525 1 TO 3 AND 526,5261 & 2 ,416, 416 1 TO 58, KELKARWADI, 400071
- Possession delayed ~3 yrs. Originally promised Dec 2023, now proposed Oct 2026 per the RERA filing.
- 12 RERA complaints. 12 complaint records are disclosed against this project on MahaRERA.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Oct 2026 per the RERA filing.
Central crossroads reborn via freeway and Metro links.
- Growth drivers:
- Eastern Freeway, Monorail/Metro, BKC proximity at half the price.
- Who buys here:
- BKC-bound professionals and long-time Chembur families.
PropPin area guide โ editorial, not a RERA disclosure.
Official RERA facts
- Registration
- P51800009799
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- October 2026originally December 2023
- Construction
- 65.2% complete
- Units sold
- 145 of 198
RERA complaint record12 records
- ComplaintCC126041342 Jul 2026Vaibhav Dilip Khade vs MANGALNATH DEVELOPERS PVT LTD
- ComplaintCC1260376018 Jun 2026Rekha Jaiswar vs MANGALNATH DEVELOPERS PVT LTD
- ComplaintCC1260272210 May 2026Ajay Gupta vs MANGALNATH DEVELOPERS PVT LTD
- ComplaintCC1260249829 Apr 2026Sharda Rohit Kandwal vs MANGALNATH DEVELOPERS PVT LTD
- ComplaintCC1260188731 Mar 2026Pooja Sachdeva vs MANGALNATH DEVELOPERS PVT LTD
- ComplaintCC126000101 Jan 2026VAIBHAV DILIP KHADE vs MANGALNATH DEVELOPERS PVT LTDFinal Order of Vaibhav Khade.pdf on MahaRERA
- ComplaintCC1250442612 Dec 2025Rekha Jaiswar vs MANGALNATH DEVELOPERS PVT LTDOrder of Rekha Jaiswar vs Mangalnath Dev (1).pdf on MahaRERA
- Misc. applicationCC1250213328 Jun 2025SURYAKANT RAMACHANDRA JADHAV vs MANGALNATH DEVELOPERS PVT LTD
- ComplaintCC1250213328 Jun 2025SURYAKANT RAMACHANDRA JADHAV vs MANGALNATH DEVELOPERS PVT LTDCC12502133.pdf on MahaRERA
- ComplaintCC1250212127 Jun 2025Urvish Mahendrabhai Modh vs MANGALNATH DEVELOPERS PVT LTDCC12502121.pdf on MahaRERA
- Misc. applicationCC1250212127 Jun 2025Urvish Mahendrabhai Modh vs MANGALNATH DEVELOPERS PVT LTD
- ComplaintCC0060000004287074 Jan 2024Praveen Pathak and Shreeya Atre vs Mangalnath Developers Pvt Ltd Earlier known as Mangalnath DevelopersOrder of Pravin Pathak.pdf on MahaRERA
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Aug 2017
- Floors
- 21
- Unit mix
- 195 res ยท 3 comm
- Architect
- CONSULTANTS COMBINED ARCHITECTS
Buyer community
Connect with other buyers and owners of SAFAL SAI AND SAFAL SAINATH โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching SAFAL SAI AND SAFAL SAINATH. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.