SAMARTH ENCLAVE H WING ANDHERI CHHAYA CHS

by SAMARTH ERECTORS AND DEVELOPERS

156PT 158 159/1 159/2 160A/1 PT, Andheri, 400093

High risk
  • Possession delayed ~2 yrs. Originally promised Dec 2024, now proposed Dec 2026 per the RERA filing.
  • Behind schedule. Possession is due Dec 2026 but construction is only at 43.4%.

Official RERA facts

Registration
P51800009806
Status
Ongoing
Stage
Certificate Signed
Possession
December 2026originally December 2024
Construction
43.4% complete
Units sold
45 of 56