All RERA projects
🏗️
Under construction

EKTA APPARTMENT FROM 18TH FLOOR TO 22ND FLOOR

by ADITYA ENTERPRISE

88, Borivali, 400066

High risk
  • Possession delayed ~5 yrs. Originally promised Dec 2021, now proposed Dec 2026 per the RERA filing.
  • Behind schedule. Possession is due Dec 2026 but construction is only at 38.8%.

Official RERA facts

Registration
P51800011046
Status
Ongoing
Stage
Certificate Signed
Possession
December 2026originally December 2021
Construction
38.8% complete
Units sold
0 of 0

RERA complaint record

Complaint data not yet synced for this project.

Discussion

No discussions yet. Booked here, visited the site, or got a quote? Share it — buyers in the same project rarely get to compare notes.

Start a discussion

Data sourced from the official MahaRERA portal. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.