Under construction

mam trilok

by LEELA ENTERPRISES

791-A, 791-B, Kurla, 400081

High risk
  • Possession delayed ~5 yrs. Originally promised Sept 2020, now proposed Mar 2026 per the RERA filing.
  • Possession date passed. The proposed possession date (Mar 2026) has passed with construction at 90.9%.

Official RERA facts

Registration
P51800011162
Status
Ongoing
Stage
Certificate Signed
Possession
March 2026originally September 2020
Construction
90.9% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 20 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply85%
Sewerage (Chamber, Lines, Septic Tank , STP)85%
Storm Water Drainsdone
Solid Waste Management And Disposaldone
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirements85%
Electrical meter room, sub-station, receiving stationdone
Open Parkingnot started

Building & registration

RERA registered
Aug 2017
Floors
13

Buyer community

Connect with other buyers and owners of mam trilok โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching mam trilok. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.