Caution
  • Possession date passed. The proposed possession date (Mar 2019) has passed with construction at 90.9%.
Kandivali / BorivaliMid-income

Self-sufficient Gujarati-dominated family belt beside the National Park.

Growth drivers:
Metro 2A/7, station upgrades, big-brand township launches.
Who buys here:
Families seeking space and community at sane prices.

PropPin area guide โ€” editorial, not a RERA disclosure.

Official RERA facts

Registration
P51800011231
Status
Ongoing
Stage
Certificate Signed
Possession
March 2019originally March 2018
Construction
90.9% complete
Units sold
0 of 0

RERA complaint record1 record

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Planting20%
Water conservation /Rain water harvestingdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Open Parkingdone

Building & registration

RERA registered
Aug 2017
Floors
18

Buyer community

Connect with other buyers and owners of Aditya Aryan / Ejaj โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Aditya Aryan / Ejaj. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.