High risk
  • Possession delayed ~7 yrs. Originally promised Dec 2019, now proposed Jun 2027 per the RERA filing.

Official RERA facts

Registration
P51800011262
Status
Ongoing
Stage
Certificate Signed
Possession
June 2027originally December 2019
Construction
80.7% complete
Units sold
24 of 43