All RERA projects
🏗️
Under construction

Mayur Tower

by Geopreneur Spire Realty

Survey no. 341 part CTS no. 607, Andheri, 400051

High risk
  • Possession delayed ~8 yrs. Originally promised Mar 2019, now proposed Dec 2026 per the RERA filing.

Official RERA facts

Registration
P51800011901
Status
Ongoing
Stage
Certificate Signed
Possession
December 2026originally March 2019
Construction
87.3% complete
Units sold
52 of 127

RERA complaint record

Complaint data not yet synced for this project.

Discussion

No discussions yet. Booked here, visited the site, or got a quote? Share it — buyers in the same project rarely get to compare notes.

Start a discussion

Data sourced from the official MahaRERA portal. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.