High risk
  • Possession delayed ~7 yrs. Originally promised Dec 2020, now proposed Dec 2027 per the RERA filing.

Official RERA facts

Registration
P51800012007
Status
Ongoing
Stage
Certificate Signed
Possession
December 2027originally December 2020
Construction
39.1% complete
Units sold
141 of 147