Under construction

SHRADDHA ORCHID AVENUE

by SHRADDHA LANDMARK PRIVATE LIMITED

35 PT AND 35A, Kurla, 400078

Apr 2018
Possession
89.5%
Built
1
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Apr 2018) has passed with construction at 89.5%.
Bhandup / KanjurmargMid-income

Emerging eastern corridor between Powai and Mulund.

Growth drivers:
Metro 6 (JVLR), large land parcels turning into townships.
Who buys here:
Value-hunters betting on the corridor's growth.

PropPin area guide โ€” editorial, not a RERA disclosure.

Official RERA facts

Registration
P51800012384
Status
Ongoing
Stage
Certificate Signed
Possession
April 2018originally December 2017
Construction
89.5% complete
Units sold
0 of 0

RERA complaint record1 record

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths90%
Water Supply90%
Sewerage (Chamber, Lines, Septic Tank , STP)90%
Storm Water Drainsdone
Landscaping & Tree Planting50%
Street Lighting50%
Water conservation /Rain water harvesting50%
Fire protection and fire safety requirements90%
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Space50%
SOCIETY OFFICEdone
FITNESS CENTRE90%

Building & registration

RERA registered
Sept 2017
Floors
24

Buyer community

Connect with other buyers and owners of SHRADDHA ORCHID AVENUE โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SHRADDHA ORCHID AVENUE. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.