All RERA projects
🏗️
Under construction

Ruparel Skygreens I

by Shree Siddhivinayak Infrastructure & Realty

735, 745pt, 747pt, 748pt, 744pt, 750pt, 751pt, 752, 753, Borivali, 400067

High risk
  • Possession delayed ~4 yrs. Originally promised Dec 2022, now proposed Dec 2026 per the RERA filing.

Official RERA facts

Registration
P51800012513
Status
Ongoing
Stage
Certificate Signed
Possession
December 2026originally December 2022
Construction
78.2% complete
Units sold
405 of 481

RERA complaint record

Complaint data not yet synced for this project.