THE POLARIS

by TANVI CONSTRUCTION PVT LTD

1588/4 PART AND 1588/6 PART, DAHISAR EAST, 400068

Dec 2028
Possession
8.2%
Built
0
Complaints
503
Units
High risk
  • Possession delayed ~3 yrs. Originally promised Dec 2025, now proposed Dec 2028 per the RERA filing.

Official RERA facts

Registration
P51800014217
Status
New
Stage
Certificate Signed
Possession
December 2028originally December 2025
Construction
8.2% complete
Units sold
16 of 503

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposal50%
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Nov 2017
Floors
42
Unit mix
0 res ยท 503 comm
Architect
Space Vision Architects

Buyer community

Connect with other buyers and owners of THE POLARIS โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching THE POLARIS. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.