Lodha Patel Estate - Tower E, F

by MACROTECH DEVELOPERS LIMITED

216/A, Borivali, 400102

High risk
  • 7 RERA complaints. 7 complaint records are disclosed against this project on MahaRERA.
  • Possession date passed. The proposed possession date (Oct 2023) has passed with construction at 81.8%.
  • Promised amenities not started. Clubhouse is at 0% build with possession due Oct 2023 per the RERA filing.
Andheri WestUpper-mid

Entertainment-industry heartland — dense, lively, well connected.

Growth drivers:
Metro lines 1/2A, Lokhandwala–Versova redevelopment wave.
Who buys here:
Media professionals, first upgraders, rental investors.

PropPin area guide — editorial, not a RERA disclosure.

Official RERA facts

Registration
P51800014869
Status
New
Stage
Certificate Signed
Possession
October 2023
Construction
81.8% complete
Units sold
0 of 0

RERA complaint record7 records

  • ComplaintCC1240023426 Sept 2024
    MACROTECH DEVELOPERS LIMITED vs Arif Shabbir Qureshi
    FO CC292598.pdf on MahaRERA
  • ComplaintCC1240023526 Sept 2024
    MACROTECH DEVELOPERS LIMITED vs Arif Shabbir Qureshi
    FO CC292598.pdf on MahaRERA
  • Misc. applicationCC1240023426 Sept 2024
    MACROTECH DEVELOPERS LIMITED vs Arif Shabbir Qureshi
  • Misc. applicationCC1240023526 Sept 2024
    MACROTECH DEVELOPERS LIMITED vs Arif Shabbir Qureshi
  • ComplaintCC1240011816 Sept 2024
    Harish Kumar Gulati vs MACROTECH DEVELOPERS LIMITED
  • ComplaintCC1240012016 Sept 2024
    Namita Gulati vs MACROTECH DEVELOPERS LIMITED
  • ComplaintCC00600000029259810 Sept 2022
    Kezar Ali Kurawarwala vs M/s. Macrotech Developers Limited
    FO CC292598.pdf on MahaRERA

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Street Lightingdone
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Waterdone
Solid Waste Management And Disposaldone
Water conservation /Rain water harvestingdone
Energy managemcntnot started
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Spacenot started
Open Parkingdone

Building & registration

RERA registered
Jan 2018
Floors
22

Buyer community

Connect with other buyers and owners of Lodha Patel Estate - Tower E, F — compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet — start one and connect with the next buyer researching Lodha Patel Estate - Tower E, F. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.