All RERA projects
🏗️
Under construction

Gulab Mansion

by Jyotindrakumar Punamchand Shah

6, Ward FNorth, 400022

High risk
  • Possession delayed ~7 yrs. Originally promised Mar 2020, now proposed Aug 2027 per the RERA filing.

Official RERA facts

Registration
P51800015543
Status
Ongoing
Stage
Certificate Signed
Possession
August 2027originally March 2020
Construction
59.6% complete
Units sold
0 of 0

RERA complaint record

Complaint data not yet synced for this project.

Discussion

No discussions yet. Booked here, visited the site, or got a quote? Share it — buyers in the same project rarely get to compare notes.

Start a discussion

Data sourced from the official MahaRERA portal. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.