PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

BLOSSOM

by NATIONAL (INDIA) CONTRACTORS AND ENGINEERS

C.T.S NO. 7301/8, SANTACRUZ EAST, 400055

Dec 2024
Possession
27.3%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Dec 2024) has passed with construction at 27.3%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2024 per the RERA filing.

Official RERA facts

Registration
P51800018044
Status
New
Stage
Certificate Signed
Possession
December 2024
Construction
27.3% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Oct 2018
Floors
12

Buyer community

Connect with other buyers and owners of BLOSSOM โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching BLOSSOM. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.