Under construction

Sunteck Crest, Plot No.3, Mukund Nagar, Andheri Kurla Road, Andheri East

by Poonam Co-operative Housing Society Limited

CTS No. 189 B, Andheri, 400059

High risk
  • Possession date passed. The proposed possession date (Jan 2022) has passed with construction at 90.9%.
  • Promised amenities not started. Clubhouse is at 0% build with possession due Jan 2022 per the RERA filing.

Official RERA facts

Registration
P51800022233
Status
New
Stage
Certificate Signed
Possession
January 2022
Construction
90.9% complete
Units sold
60 of 81

RERA complaint record1 record

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Community Buildingsnot started
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Open Parkingnot started

Building & registration

RERA registered
Sept 2019
Floors
12
Unit mix
0 res ยท 81 comm
Architect
Sandeep Shikre & Associates
Public authority
Brihanmumbai Municipal Corporation (BMC)

Buyer community

Connect with other buyers and owners of Sunteck Crest, Plot No.3, Mukund Nagar, Andheri Kurla Road, Andheri East โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Sunteck Crest, Plot No.3, Mukund Nagar, Andheri Kurla Road, Andheri East. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.