VISHAL SHILP

by SHRADDHA SKYLINE LLP

CTS 5662 PT FP NO 311 PT, Kurla, 400075

High risk
  • Possession date passed. The proposed possession date (Jun 2021) has passed with construction at 90.9%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2021 per the RERA filing.

Official RERA facts

Registration
P51800022851
Status
New
Stage
Certificate Signed
Possession
June 2021
Construction
90.9% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 20 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacedone
Open Parkingnot started

Building & registration

RERA registered
Oct 2019
Floors
18

Buyer community

Connect with other buyers and owners of VISHAL SHILP โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching VISHAL SHILP. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.