Under construction

KANAKIA ZENWORLD PHASE II

by KANAKIA SPACES REALTY PRIVATE LIMITED

1015, 1015/1 TO 3, Kurla, 400042

Caution
  • Possession date passed. The proposed possession date (Jun 2026) has passed with construction at 88.6%.

Official RERA facts

Registration
P51800022936
Status
New
Stage
Certificate Signed
Possession
June 2026
Construction
88.6% complete
Units sold
0 of 0

RERA complaint record1 record

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supply95%
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Street Lightingdone
Community Buildingsdone
Treatment And Disposal Of Sewage And Sullage Waterdone
Solid Waste Management And Disposaldone
Water conservation /Rain water harvestingdone
Energy managemcnt95%
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Nov 2019
Floors
39
Architect
Mr. Harsh Pote

Buyer community

Connect with other buyers and owners of KANAKIA ZENWORLD PHASE II โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching KANAKIA ZENWORLD PHASE II. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.