All RERA projects
🏗️
Under construction

Vivaana Heights

by N K BUILDERS & DEVELOPERS

939 of TPS IV Mahim Division and Contiguous 12.20 mts. wide D. P. Road, Andheri, 400025

High risk
  • Possession date passed. The proposed possession date (Jun 2026) has passed with construction at 44.3%.

Official RERA facts

Registration
P51800025788
Status
New
Stage
Certificate Signed
Possession
June 2026
Construction
44.3% complete
Units sold
1 of 1

RERA complaint record

Complaint data not yet synced for this project.

Discussion

No discussions yet. Booked here, visited the site, or got a quote? Share it — buyers in the same project rarely get to compare notes.

Start a discussion

Data sourced from the official MahaRERA portal. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.