AUBBURN WING C

by S D CORPORATION PRIVATE LIMITED

840 A/1 PART, Borivali, 400101

High risk
  • Possession delayed ~3 yrs. Originally promised Jun 2024, now proposed Jun 2027 per the RERA filing.
  • Behind schedule. Possession is due Jun 2027 but construction is only at 44.3%.

Official RERA facts

Registration
P51800026064
Status
New
Stage
Certificate Signed
Possession
June 2027originally June 2024
Construction
44.3% complete
Units sold
95 of 97

RERA complaint record

Complaint data not yet synced for this project.