All RERA projects
🏗️
Under construction

SHRADHA RESIDENCY

by KONARK SHRADHA REALTORS

CTS 72, 72/1 to 10, Andheri, 400058

High risk
  • Possession delayed ~3 yrs. Originally promised Jun 2023, now proposed Jun 2026 per the RERA filing.
  • Possession date passed. The proposed possession date (Jun 2026) has passed with construction at 55.9%.

Official RERA facts

Registration
P51800027190
Status
New
Stage
Certificate Signed
Possession
June 2026originally June 2023
Construction
55.9% complete
Units sold
13 of 61

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 17 Jul 2026).

Discussion

No discussions yet. Booked here, visited the site, or got a quote? Share it — buyers in the same project rarely get to compare notes.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 17 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.