ASHOKA GRANDEUR

by DHANRAJ DEVELOPERS

408 PT, 412 PT, 412/10 TO 412/17, 412/19, BHANDUP WEST, 400078

Jun 2028
Possession
20.5%
Built
1
Complaints
205
Units
High risk
  • Possession delayed ~3 yrs. Originally promised Dec 2024, now proposed Jun 2028 per the RERA filing.
Bhandup / KanjurmargMid-income

Emerging eastern corridor between Powai and Mulund.

Growth drivers:
Metro 6 (JVLR), large land parcels turning into townships.
Who buys here:
Value-hunters betting on the corridor's growth.

PropPin area guide โ€” editorial, not a RERA disclosure.

Official RERA facts

Registration
P51800027876
Status
New
Stage
Certificate Signed
Possession
June 2028originally December 2024
Construction
20.5% complete
Units sold
35 of 205

RERA complaint record1 record

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Jan 2021
Floors
22
Unit mix
188 res ยท 17 comm

Buyer community

Connect with other buyers and owners of ASHOKA GRANDEUR โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching ASHOKA GRANDEUR. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.