AMANN HIGHLAND PARK

by MS RELLIANCE CONSTRUCTION CO

738/B/1/A, Borivali, 400097

High risk
  • Possession delayed ~1 yr. Originally promised Jun 2025, now proposed Oct 2026 per the RERA filing.
  • Behind schedule. Possession is due Oct 2026 but construction is only at 44.6%.

Official RERA facts

Registration
P51800028085
Status
New
Stage
Certificate Signed
Possession
October 2026originally June 2025
Construction
44.6% complete
Units sold
86 of 231