Pratap Grandeur

by M/S JPV REALTORS

CTS NO 346, Borivali, 400097

High risk
  • Possession delayed ~2 yrs. Originally promised Jun 2025, now proposed Jun 2027 per the RERA filing.
  • Behind schedule. Possession is due Jun 2027 but construction is only at 47.7%.

Official RERA facts

Registration
P51800028713
Status
New
Stage
Certificate Signed
Possession
June 2027originally June 2025
Construction
47.7% complete
Units sold
12 of 16

RERA complaint record

Complaint data not yet synced for this project.