All RERA projects
🏗️
Under construction

SAFAL MONTBAY

by JAI MATA DI HOME CONSTRUCTION PVT LTD

CTS NO 390A, Kurla, 400088

High risk
  • Possession delayed ~3 yrs. Originally promised Apr 2025, now proposed Sept 2028 per the RERA filing.

Official RERA facts

Registration
P51800028789
Status
New
Stage
Certificate Signed
Possession
September 2028originally April 2025
Construction
0% complete
Units sold
0 of 0

RERA complaint record

Complaint data not yet synced for this project.